Dimensionnement et exploitation d'une station d'épuration à boue activé cas step d'ain el kihal
Loading...
Date
Journal Title
Journal ISSN
Volume Title
Publisher
Abstract
We noticed that the wastewater coming from Ain Kihal and Sidi Zaydour are throw directely
to a valley without any treatement, as a result of that many problems had appeared so the best
solution is the build of a wastewater treatement plant.
We did this project in order to do a study of the area, choose a suitable place of the future
plant witch is still in progress, then we will do a specific sizing of the future wastewater plant
after of course the knowledge of the wastewater debit and the number of the population each
10 years from 2015 to 2050.
We found that each 10 years the population rise and the wastewater rise too, so we must do an
extension after reaching 2050.