This work consists of both studying the operation of the 3 × 400 MW TERGA
Combined Cycle Power Plant located in Ain Témouchent, and understanding the supervision
process put in place for the management and monitoring of the control system. To do this, we
have defined thermal power plants in Algeria as well as the various existing types. Then, we
gave the description and general operation of the TERGA 3 × 400 MW Combined Cycle
Power Plant with their different zones. Then, we approached industrial supervision in general
and gave the supervision process of the TERGA 3 × 400 MW Combined Cycle Power Plant
more specifically; And finally, we took a concrete example of boiler supervision and saw how
we could monitor and control the levels of the three balloons.